TILT PANELS UP

• In-ground services have been installed

• Strip and pad footings are complete

• All concrete panels have been poured for Blocks A and B, with
pouring now underway for Block C

• Tilt panels have now been erected for Blocks A and B.

Practical completion forecast for November 2025.

25 August 2025